Extension for RAI responses delays Project Ike review
In a decision that potentially has added two months to its projected review timeline, the Nuclear Regulatory Commission has given Orano Enrichment more time to respond to the commission’s requests for additional information regarding the Project Ike Enrichment Facility. The NRC began an accelerated technical review of Orano’s license application for the Oak Ridge, Tenn., facility in May of this year. In its May 21 letter announcing its acceptance of Orano’s application, the NRC stated that it planned to complete the expedited review by April 30, 2027.